Energy Parks

  • Special Settlement team for Energy Projects Land
  • 1500 Acres Kuchlaq Land disputed
  • 1500 Acres of Land at Panjpai identified
  • 1000 Acres of Land at Hazar Ganji Quetta
  • Meetings held with SMBR, Commissioners & DCs

a)5000 acres of land at Sibi / Bolan for Energy Parks (CSP)

b)10000 acres of land at Nokundai for Energy Parks (Wind)

c)2000 acres each at QSF (Solar)

d)1000 acres at Mastung, Pishin, Khuzdar, Loralai, Panjgur & Lasbella for Energy Parks (Solar)

Institutional Strengthening

  • Energy Complex proposal initiated
  • Divisional Offices & Staff proposal initiated
  • SNE of 25 posts of Oil & Gas Directorate initiated
  • Experts hiring under process
  • EU Assistance for Technical, Legal & IT Experts
  • Secretary Energy office Renovated
  • Vehicles request would be placed shortly

Renewable Energy

  • 10 Thousand Solar homes for Disabled persons under CPEC
  • 10 LOIs issued to Engro Energy for 500MW Wind Plants
  • Feasibility study for the wind plants at Nokundi under process
  • Grid Connectivity Feasibility done through private sector
  • Work initiated on the 1st RE policy of GoB

Study conducted for Restoration of Street lights of Quetta

Oil & Gas Sector

  • Federal Energy Minister meeting with Honorable CM Balochistan on 14th Nov 2019
  • PM Performance Unit notified to review pending energy issues
  • Development of Oil & Gas Directorate proposal initiated
  • Director DGPC Interviews on 11th Feb 2020
  • Hiring of Technical Expert on Oil & Gas under process

 

Proposed Projects for PSDP (2020-21)

S.No. Project Title Estimated Cost

In PKR.

1. Solar Power facility in DHQ Hospitals / RHCs in Balochistan 809.79 Million.
2. Solar Power facility in BHUs & ECs 600.00 Million.
3. Solar Streets lights in all Districts of Balochistan (Approx: 100 lights for each) 680.00 Million.
4. 01 MW Solar Power Plant 160.00 Million.
5. Solar Homes under PPP mode in few selected districts on pilot bases 100.00 Million.
6. Research & Development Studies. 100.00 Million
Total: 2449.79 Million

 

Regular Initiatives:

  • Amendments in Electricity Rules, 1937
  • Impact: Electricity inspection charges to be increased from 10 Million to 50 Million
  • Amendments in Finance Act, 1964
  • Impact: Electricity duty enhanced by 1.5%, Revenue would increase from Rs. 3 million P/month to Rs.6.5 million P/month

Equity / Rental for Power Projects

  • Sub lease Signed for 300 MW Power Plant at Gwadar with CIHC Pak Power Company
  • Rs. 500 million transferred to GoB against the land lease, while Rs. 25 mn A/Rent to be paid
  • 8% equity partnership against land with Eneretech for the RE Plants at Pishin
  • 3% Equity share negotiations with HUBCO
  • Equity share negotiations with PARCO